1 | Q/YZJ.J0297-2020 | Temporary stiffener splice length and welding node standards | 2020/3/31 |
2 | Q/NYZ.J02125-2021 | Construction process standards for OBO cargo hatch coaming | 2021/9/8 |
3 | Q/NYZ.J0218-2021 | Thermosetting coating process standards for special coating compartments | 2021/9/8 |
4 | Q/YZJ.J0201-2019 | Submerged arc automatic welding general welding process standards | 2019/10/6 |
5 | Q/YZJ.J0202-2019 | Manual arc welding general welding process standards | 2019/10/6 |
6 | Q/YZJ.J0203-2019 | CO2 semi-automatic welding single-side porcelain pad butt welding process standards | 2019/10/6 |
7 | Q/YZJ.J0204-2019 | Welding process standards for high-strength steel | 2019/10/6 |
8 | Q/YZJ.J0205-2019 | Stainless steel pipe welding process standards | 2019/10/6 |
9 | Q/YZJ.J0206-2019 | Cast steel welding process standards | 2019/10/6 |
10 | Q/YZJ.J0207-2021 | Welded seam standards for steel hull | 2022/1/12 |
11 | Q/YZJ.J0208-2019 | Welding process standards for copper-nickel alloy pipes | 2019/9/24 |
12 | Q/YZJ.J0209-2019 | Pipeline welding process standards | 2019/9/24 |
13 | Q/YZJ.J0210-2019 | Ship coating technical standards | 2019/9/25 |
14 | Q/YZJ.J02100-2019 | Installation process standards for eccentric platform Stülcken crane | 2019/9/25 |
15 | Q/YZJ.J02101-2019 | Process standards for container spreader fabrication | 2019/9/23 |
16 | Q/YZJ.J02102-2019 | Installation process for detachable hatch cover | 2019/9/23 |
17 | Q/YZJ.J02103-2020 | Coating process standards for outfitting parts and pipelines | 2020/6/8 |
18 | Q/YZJ.J02104-2019 | Profiles and processing standards for outfitting parts | 2019/7/1 |
19 | Q/YZJ.J02105-2021 | Marinline coating application technology standards | 2021/3/16 |
20 | Q/YZJ.J02106-2019 | Electrical cable identification process | 2019/9/26 |
21 | Q/YZJ.J02107-2019 | Conventional electrical equipment installation process for ships | 2019/9/26 |
22 | Q/YZJ.J02108-2019 | Waveguide and fiber optic cable laying process requirements | 2019/9/26 |
23 | Q/YZJ.J02109-2019 | Installation process standards for composite rock wool board in compartments | 2019/9/18 |
24 | Q/YZJ.J0211-2019 | PSPC coating process standards | 2019/9/25 |
25 | Q/YZJ.J02110-2019 | Compartment and deck covering construction process standards | 2019/9/18 |
26 | Q/YZJ.J02110-2021 | Compartment and deck covering construction process | 2021/4/1 |
27 | Q/YZJ.J02111-2019 | Installation process for ceramic cotton and rock wool fiber boards | 2019/9/18 |
28 | Q/YZJ.J02112-2019 | Installation process for modular refrigeration units on ships | 2019/9/18 |
29 | Q/YZJ.J02113-2019 | Installation process for fire doors in compartments | 2019/9/18 |
30 | Q/YZJ.J02114-2019 | Installation process for separate window pieces | 2019/4/30 |
31 | Q/YZJ.J02115-2019 | Production and installation process for windowsills | 2019/4/30 |
32 | Q/YZJ.J02115-2020 | Production and installation process for wooden windowsills in wheelhouse | 2020/7/1 |
33 | Q/YZJ.J02116-2019 | Process for fabrication of container corner posts | 2019/9/23 |
34 | Q/YZJ.J02117-2019 | Process for fabrication and installation of lashing bridges on container ships | 2019/9/25 |
35 | Q/YZJ.J02118-2019 | Unbacked joining process standards for profiles (Chinese-English) | 2019/3/27 |
36 | Q/YZJ.J02119-2019 | Visual operation standards for correcting excessive grinding of welds (Chinese-English) | 2019/4/18 |
37 | Q/YZJ.J0212-2019 | Surface treatment standards for steel materials before coating | 2019/9/25 |
38 | Q/YZJ.J02120-2019 | Deformation control process standards for thin plates | 2019/10/30 |
39 | Q/YZJ.J02121-2020 | Sealing process standards for cable penetrations | 2020/6/11 |
40 | Q/YZJ.J02122-2019 | Rib-pulling construction process standards for segmented hull | 2019/7/4 |
41 | Q/YZJ.J02123-2019 | Lifting installation process standards for entire hatch coaming | 2019/7/1 |
42 | Q/YZJ.J02124-2019 | New single-side continuous welding process standards for temporary reinforcements on upper structure | 2019/9/18 |
43 | Q/YZJ.J02125-2019 | Construction process standards for OBO cargo hatch coaming | 2019/8/27 |
44 | Q/YZJ.J02127-2021 | Antenna installation process | 2022/7/6 |
45 | Q/YZJ.J02128-2020 | Process standards for installation of oil suction wells on ships | 2020/6/9 |
46 | Q/YZJ.J02129-2020 | Anti-corrosion process standards for various outfitting parts on exposed deck | 2020/8/6 |
47 | Q/YZJ.J0213-2019 | Fabrication process standards for hull blocks | 2021/3/10 |
48 | Q/YZJ.J02130-2021 | Excel form standards for rapid completion of loading conditions | 2021/9/1 |
49 | Q/YZJ.J02131-2021 | Renewal standards for hull structure of repaired ships | 2021/7/6 |
50 | Q/YZJ.J02132-2021 | Watertight test standards after repair of hull structure | 2021/9/1 |
51 | Q/YZJ.J02133-2021 | Technical standards for repair of bilge drain plugs | 2021/4/1 |
52 | Q/YZJ.J02134-2021 | Technical standards for replacement of sacrificial anodes on ships | 2021/4/27 |
53 | Q/YZJ.J02135-2021 | Technical requirements for repair of ship railings | 2021/6/3 |
54 | Q/YZJ.J02136-2021 | Technical standards for repair of small steel hatch covers on ships | 2021/7/6 |
55 | Q/YZJ.J02137-2021 | Technical standards for repair of steel doors on ships | 2021/9/1 |
56 | Q/YZJ.J02138-2021 | Technical standards for repair of fixed steel ladders on ships | 2021/9/1 |
57 | Q/YZJ.J02139-2021 | Technical standards for repair of cargo hold hatch covers on ships | 2022/7/6 |
58 | Q/YZJ.J0214-2012 | Erection process standards for hull block integration | 2019/10/6 |
59 | Q/YZJ.J02140-2021 | Technical standards for repair of general ventilation systems on ships | 2022/7/6 |
60 | Q/YZJ.J02141-2021 | Technical standards for repair of galley and laundry equipment on ships | 2021/4/1 |
61 | Q/YZJ.J02142-2021 | Technical standards for repair of steel windows on ships | 2021/4/1 |
62 | Q/YZJ.J02143-2021 | Technical standards for repair of wooden furniture on ships | 2021/6/3 |
63 | Q/YZJ.J02144-2021 | Technical standards for repair of refrigerators on ships | 2021/6/3 |
64 | Q/YZJ.J02145-2021 | Technical standards for repair of deck coverings on ships | 2021/9/1 |
65 | Q/YZJ.J02146-2021 | Technical standards for repair of fire, thermal and acoustic insulation on ships | 2021/9/1 |
66 | Q/YZJ.J02147-2021 | Technical standards for repair of compartment doors on ships | 2022/7/6 |
67 | Q/YZJ.J02148-2021 | Technical standards for repair of sanitary units in compartments on ships | 2022/7/6 |
68 | Q/YZJ.J02149-2021 | Technical standards for repair of marine electric motors | 2021/3/25 |
69 | Q/YZJ.J0215-2020 | Passivation process for pickling of stainless steel pipes | 2020/6/11 |
70 | Q/YZJ.J02150-2021 | Technical standards for repair of switchboards on ships | 2021/4/21 |
71 | Q/YZJ.J02151-2021 | Technical standards for repair and laying of cables on ships | 2021/5/26 |
72 | Q/YZJ.J02152-2021 | Technical standards for repair of distribution boxes on ships | 2021/7/6 |
73 | Q/YZJ.J02153-2021 | Technical standards for repair of electrical control boxes on ships | 2021/7/6 |
74 | Q/YZJ.J02154-2021 | Technical standards for repair and test of automation systems in ship power stations | 2021/9/1 |
75 | Q/YZJ.J02155-2021 | Technical standards for repair and test of engine room monitoring and alarm systems on ships | 2021/9/1 |
76 | Q/YZJ.J02156-2021 | Technical standards for repair and test of remote control systems for main engines on ships | 2021/9/1 |
77 | Q/YZJ.J02157-2021 | Technical standards for repair of batteries on ships | 2022/7/6 |
78 | Q/YZJ.J0216-2019 | Installation process standards for outfitting parts in segments | 2019/4/30 |
79 | Q/YZJ.J02163-2021 | Coating process standards for ship repair | 2022/7/6 |
80 | Q/YZJ.J02164-2021 | Survey and inspection technical standards for propulsion shafting system repair on ships | 2021/9/9 |
81 | Q/YZJ.J02165-2021 | Technical standards for repair of propeller tail shaft, intermediate shaft, thrust shaft and couplings on ships | 2021/9/9 |
82 | Q/YZJ.J02166-2021 | Technical standards for repair of shaft system bearings, stern tube and pipelines on ships | 2021/9/9 |
83 | Q/YZJ.J02167-2021 | Technical standards for repair of marine valves | 2021/9/9 |
84 | Q/YZJ.J0217-2019 | Process standards for fabrication and installation of piping system on ships | 2019/10/17 |
85 | Q/YZJ.J02171-2022 | Installation process for sea chests | 2022/7/1 |
86 | Q/YZJ.J0218-2019 | Thermosetting coating process standards for special coating compartments | 2019/10/24 |
87 | Q/YZJ.J0219-2020 | Full process control procedures for stainless steel pipes | 2020/11/30 |
88 | Q/YZJ.J0220-2019 | Process standards for fabrication and installation of rudders | 2021/3/10 |
89 | Q/YZJ.J0221-2019 | Pre-installation process standards for container guide rails in cargo holds | 2019/9/23 |
90 | Q/YZJ.J0222-2021 | Reinforcement standards for deformation prevention of upper structure | 2021/4/29 |
91 | Q/YZJ.J0223-2019 | Draft mark measurement process | 2019/4/30 |
92 | Q/YZJ.J0223-2021 | Installation process standards for draft marks on ships | 2021/4/27 |
93 | Q/YZJ.J0224-2019 | Installation process standards for container corner posts | 2019/9/25 |
94 | Q/YZJ.J0225-2019 | Positioning and installation process for outer shell frames | 2019/9/29 |
95 | Q/YZJ.J0226-2019 | Lifting and suspension code standards for hulls | 2019/7/4 |
96 | Q/YZJ.J0227-2020 | Grounding process standards for electrical equipment and cables | 2020/6/9 |
97 | Q/YZJ.J0228-2019 | Process standards for electrical restoration of second-hand crude oil carriers | 2019/10/31 |
98 | Q/YZJ.J0229-2019 | Preheating standards for welding of ordinary and high strength structural steel for hull structures | 2019/10/6 |
99 | Q/YZJ.J0230-2019 | Permanent retention or removal process standards for some fixtures (Chinese-English) | 2019/3/27 |
100 | Q/YZJ.J0231-2019 | Hydrostatic test standards (Chinese-English) | 2019/3/27 |
101 | Q/YZJ.J0232-2019 | Variable frequency cable connection and installation process standards | 2019/12/3 |
102 | Q/YZJ.J0233-2019 | Installation process standards for steel furniture on ships | 2019/7/4 |
103 | Q/YZJ.J0234-2021 | Process standards for fabrication of deck cable junction boxes | 2021/3/25 |
104 | Q/YZJ.J0235-2019 | Regulations on cleaning various oil tanks/lockers and pipelines/oil filling on ships | 2019/12/12 |
105 | Q/YZJ.J0236-2019 | Installation standards for main engine low pressure SCR | 2019/7/31 |
106 | Q/YZJ.J0237-2019 | Weld height control standards for woodchip carriers | 2019/4/30 |
107 | Q/YZJ.J0238-2019 | Welding procedures for 15CrMoG alloy steel pipes | 2019/8/22 |
108 | Q/YZJ.J0239-2020 | Key points for design of FRAMO hydraulic and liquid cargo systems | 2020/6/11 |
109 | Q/YZJ.J0240-2020 | Process standards for fabrication and installation of folding supports for cargo guide rails | 2020/5/25 |
110 | Q/YZJ.J0241-2020 | Design process standards for lashing bridges | 2020/3/31 |
111 | Q/YZJ.J0242-2020 | Design and fabrication process standards for lashing platforms | 2020/6/9 |
112 | Q/YZJ.J0243-2020 | Welding and installation process for lashing parts | 2020/7/1 |
113 | Q/YZJ.J0244-2019 | Process flows | 2019/9/29 |
114 | Q/YZJ.J0245-2019 | Lifting and reinforcement design standards | 2019/7/4 |
115 | Q/YZJ.J0246-2020 | Installation process standards for hatch coaming guide rails (door trolley guide rails) | 2020/5/25 |
116 | Q/YZJ.J0247-2020 | Construction conventions for liquid cargo ships | 2020/7/1 |
117 | Q/YZJ.J0248-2020 | Process standards for fabrication and installation of foldable/telescopic masts | 2020/9/30 |
118 | Q/YZJ.J0249-2020 | Lifting, transportation and installation process for Stülcken crane jibs and towers | 2020/9/8 |
119 | Q/YZJ.J0250-2019 | Safety requirements for pickling and passivation of stainless steel pipes | 2019/4/15 |
120 | Q/YZJ.J0251-2020 | Installation process for single-rail cranes | 2020/5/25 |
121 | Q/YZJ.J0252-2020 | Process standards for noise testing | 2020/3/31 |
122 | Q/YZJ.J0253-2019 | Scheme standards for typical segmental division and overall lifting schemes for entire ships | 2019/9/18 |
123 | Q/YZJ.J0254-2020 | Process standards for fabrication and installation of anchor pockets | 2020/5/29 |
124 | Q/YZJ.J0254-2021 | Process standards for fabrication of anchor pockets | 2021/3/25 |
125 | Q/YZJ.J0255-2019 | Process standards for fabrication and installation of saddles on LNG carriers | 2019/11/25 |
126 | Q/YZJ.J0256-2019 | Installation process standards for gravity davit lifeboat handling systems | 2019/9/23 |
127 | Q/YZJ.J0257-2019 | Construction conventions for coating work of superstructures | 2019/9/28 |
128 | Q/YZJ.J0258-2019 | Pull line positioning process standards for installation of mooring equipment | 2019/9/25 |
129 | Q/YZJ.J0259-2019 | Installation process standards for Stülcken crane trunks | 2019/9/24 |
130 | Q/YZJ.J0260-2019 | Process standards for preheating records of steel outfitting parts | 2019/4/15 |
131 | Q/YZJ.J0261-2019 | Installation process standards for elevators | 2019/9/25 |
132 | Q/YZJ.J0262-2019 | Installation process standards for rolling hatch covers | 2019/9/23 |
133 | Q/YZJ.J0263-2019 | Installation procedure standards for propulsion shafting (technically applicable) | 2019/8/27 |
134 | Q/YZJ.J0264-2019 | Installation procedure standards for steering gear (technically applicable) | 2019/8/27 |
135 | Q/YZJ.J0265-2019 | Scheme standards for building molding docks in segments | 2019/9/18 |
136 | Q/YZJ.J0265-2020 | Scheme standards for building sub-erection warehouses after undocking of segments | 2020/8/4 |
137 | Q/YZJ.J0266-2019 | Scheme standards for typical assembly and its temporary supports | 2019/9/24 |
138 | Q/YZJ.J0267-2020 | Selection and installation process standards for marine fans | 2020/6/9 |
139 | Q/YZJ.J0268-2019 | ICCP installation process standards | 2019/9/25 |
140 | Q/YZJ.J0269-2019 | Measurement process standards for navigation lights | 2019/9/23 |
141 | Q/YZJ.J0270-2019 | General process for installation of hatch seal (revised) | 2019/6/4 |
142 | Q/YZJ.J0271-2019 | Installation process for corner fittings and lashing pads | 2019/9/25 |
143 | Q/YZJ.J0272-2020 | Process standards for anchor chain release test | 2020/9/8 |
144 | Q/YZJ.J0273-2019 | Installation standards for composite rock wool boards and ceiling elements | 2019/9/18 |
145 | Q/YZJ.J0274-2019 | Construction process standards for deck coverings (damping) | 2019/9/18 |
146 | Q/YZJ.J0275-2019 | Construction conventions for non-skid areas on container ships | 2019/9/28 |
147 | Q/YZJ.J0276-2019 | Scheme standards for overall scaffolding design | 2019/9/18 |
148 | Q/YZJ.J0277-2019 | Process standards for preparation of outfitting supply list | 2019/9/24 |
149 | Q/YZJ.J0278-2019 | Installation process standards for anchor windlasses | 2019/9/25 |
150 | Q/YZJ.J0279-2021 | Technical guidance for design and construction of anchorage systems | 2021/5/26 |
151 | Q/YZJ.J0280-2019 | Installation technical guide for bow thrusters | 2019/9/24 |
152 | Q/YZJ.J0281-2019 | Overall scheme standards for hydrostatic test | 2019/9/18 |
153 | Q/YZJ.J0282-2019 | Scheme standards for rapid erection | 2019/9/18 |
154 | Q/YZJ.J0283-2019 | Cable laying process | 2019/6/3 |
155 | Q/YZJ.J0284-2020 | Installation process for log and echo sounder transducers | 2020/5/30 |
156 | Q/YZJ.J0285-2020 | Installation process for sacrificial anodes | 2020/6/9 |
157 | Q/YZJ.J0286-2017 | Application technology standards for flake glass paints | 2019/9/26 |
158 | Q/YZJ.J0287-2019 | Application technology standards for silicone coatings | 2019/9/25 |
159 | Q/YZJ.J0288-2019 | Construction process standards for single-layer epoxy coating in engine rooms | 2019/9/28 |
160 | Q/YZJ.J0289-2019 | Coating construction process standards for liquid cargo ships (Chinese-English) | 2019/6/27 |
161 | Q/YZJ.J0290-2020 | Construction process standards for PVC floors and rubber floors | 2020/5/21 |
162 | Q/YZJ.J0291-2020 | Cooperation process standards between semi-floating dock and full-floating undocking conditions | 2020/9/24 |
163 | Q/YZJ.J0292-2019 | Standards for grinding range on free edges of hull structural parts | 2019/7/4 |
164 | Q/YZJ.J0293-2020 | Process standards for fabrication of cradles | 2020/9/8 |
165 | Q/YZJ.J0294-2019 | Principle process standards for flame straightening | 2019/7/4 |
166 | Q/YZJ.J0295-2020 | Transportation process standards for outsourced blocks | 2020/11/30 |
167 | Q/YZJ.J0296-2019 | Principle process standards for docking and undocking | 2019/11/25 |
168 | Q/YZJ.J0298-2019 | Fabrication standards for corrugated exhaust pipes | 2019/10/16 |
169 | Q/YZJ.J0299-2019 | Installation standards for fire flaps | 2019/10/17 |
Quality Standards for Gas Carrier Construction
序号 | 标准号 | Process standard content | 编制日期 |
---|---|---|---|
1 | YAMIC/YOEWI09-77-2023 | Gas carrier quality inspection procedure | 2023-7 |
2 | YAMIC/YOEWI09-78-2023 | Inspection and test plan for 40K m3 LPG | 2023-7 |
3 | YAMIC/YOEWI09-79-2023 | Gas carrier cargo tank inspection standard (ISO5817) | 2023-7 |
4 | YAMIC/YOEWI09-80-2023 | Inspection work standards for dome and interbarrier space of 40K m3 LPG before and after heat treatment (trial) | 2023-7 |
5 | YAMIC/YOEWI09-82-2023 | Key points at various construction stages of gas carrier | 2023-7 |
6 | YAMIC/YOEWI09-83-2023 | FAT standard for gas carrier | 2023-7 |
7 | YAMIC/YOEWI09-90-2023 | Accuracy control standards for cargo tanks of 40K m3 LPG | 2023-7 |
8 | YAMIC/YOEWI09-92-2023 | Production and circulation standards for test plates of gas carrier | 2023-7 |
9 | YAMIC/YOEWI09-99-2023 | Welding procedure preparation standards for 40K m3 LPG | 2023-7 |
10 | YAMIC/YOEWI09-100-2023 | Training work standards for welders of gas carrier | 2023-7 |
11 | YAMIC/YOEWI09-101-2023 | NDT operation standards for 40K m3 LPG | 2023-7 |
船舶通用细节质量标准
-
驾控台
-
Main engine
-
Cables
-
Engine room
-
Engine room piping
-
Engine control room
-
Generator
-
Engine room
-
Draft marks
-
Shell plate lines
-
Overall appearance
液罐通用细节质量标准
-
Dedicated storage areafor special materials
-
Distinction of workshop primer for special materials
-
Excellent cutting accuracy
-
Manufacture of sub-assembly of tank
-
9Ni steel welding
-
Welding of stainless steel pipeline
-
Construction protection
-
Accuracy control of saddle and wood block
-
Pipeline cleaning
-
Internal cleaning of tank
-
Manufacture of cargo handling system module
-
Tank flatness
-
Finished products